Markets · Data centers

Transformers and storage for data centers

For campuses and powered shells where energization is the critical path: main substation transformers, site distribution and battery storage, specified to your utility and redundancy requirements.

Energization sets the schedule

For many new campuses, the date the site can take power is set by electrical equipment rather than by construction. Transformer lead times have become a gating item. We help developers and owners secure main substation and site distribution equipment early, with price, lead time and delivery terms confirmed in writing.

What we supply for a campus

ScopeEquipmentTypical range
Main substationPower transformers230 kV class, 40–300 MVA
Site distributionPad-mount and station-type5–36 kV, to 8.8 MVA; FR3 option
Phased blocksCompact and prefabricated substationsTo 12.5 MVA
StorageBattery energy storageC&I to utility scale

Built for phased campuses

  • Repeatable specifications so each phase can be ordered as a block
  • Equipment sized to your redundancy architecture (N, N+1, 2N)
  • Storage options for resilience or where grid capacity arrives in stages
  • FOB, CIF or DDP delivery to suit your construction schedule

What to include in a request

  • Load per phase (MW) and energization date for each phase
  • Utility service voltage and interconnection requirements
  • Redundancy architecture
  • Single-line diagram, if available
  • Distribution voltages (for example 34.5 kV / 480 V)
  • Interest in storage and its purpose